BENCH: Justice Sanjay Kumar and Justice
Satish Chandra Sharma
FACTS:
The appellant, Glencore International AG, a
Swiss company engaged in mining and commodity trading, had a long-standing
business relationship with respondent No.1, Shree Ganesh Metals, a
proprietorship concern in Himachal Pradesh manufacturing zinc alloys. Between
2011 and 2012, the parties entered into four contracts for the supply of zinc,
each containing an arbitration clause referring disputes to the London Court of
International Arbitration (LCIA) with London as the seat. In 2016, they
negotiated a fifth contract for the supply of 6,000 metric tons of zinc to be
delivered between March 2016 and February 2017. The terms were settled via
email correspondence, including a modification by respondent No.1 regarding the
calculation of provisional price, which was accepted by the appellant. Pursuant
to this, Glencore forwarded Contract No. 061-16-12115-S (signed by it)
incorporating the agreed terms, including an arbitration clause (Clause 32.2).
Although respondent No.1 did not sign the contract, it accepted delivery of
2,000 metric tons of zinc, acknowledged the contract in correspondence, and
facilitated the issuance of standby letters of credit through HDFC Bank that
specifically referred to the said contract.
Disputes arose in September 2016 over
pricing and failure to furnish letters of credit for subsequent quotas.
Glencore raised claims for compliance and costs, while respondent No.1 assured
performance and acknowledged obligations under the contract. Eventually, due to
continued defaults, Glencore encashed standby letters of credit, leading
respondent No.1 to file a civil suit before the Delhi High Court in 2017
seeking declaration that such invocation was null and void, recovery of USD 1.2
million, and injunctions against further encashment. In response, Glencore
invoked Section 45 of the Arbitration and Conciliation Act, 1996, seeking
reference of disputes to arbitration under Clause 32.2 of the 2016 contract.
The Single Judge of the Delhi High Court (02.11.2017) and later the Division
Bench (14.11.2019) rejected this plea, holding that no concluded contract
containing an arbitration clause existed since respondent No.1 had not signed
the 2016 agreement. Glencore, aggrieved by these findings, carried the matter
to the Supreme Court.
ISSUES:
The primary issue in this case was whether
Contract No. 061-16-12115-S, though unsigned by respondent No.1, constituted a
valid and binding agreement, particularly with respect to the arbitration
clause (Clause 32.2). The Court needed to determine whether the appellant could
invoke the arbitration agreement under Section 45 of the Arbitration and
Conciliation Act, 1996, given that the respondent argued no concluded contract
existed. An ancillary issue raised by the appellant was whether, alternatively,
the arbitration clause in the 2012 contract could apply to the 2016
transaction.
JUDGEMENT WITH REASONING:
The Supreme Court allowed the appeal,
setting aside the judgment of the Division Bench (14.11.2019) and the order of
the Single Judge (02.11.2017) of the Delhi High Court. The Court restored I.A.
No. 4550 of 2017 in CS (Comm) No. 154 of 2017, directing that the disputes
between the parties be referred to arbitration under Clause 32.2 of Contract
No. 061-16-12115-S.
The Court held that the Division Bench and
the Single Judge failed to consider crucial facts demonstrating that Contract
No. 061-16-12115-S was duly accepted and acted upon by respondent No.1, even
though it was not signed. The appellant supplied 2,000 metric tons of zinc
metal, raised invoices referencing the contract, and respondent No.1
facilitated Standby Letters of Credit in compliance with the contract terms.
Email correspondence further showed that respondent No.1 had agreed to the
contract’s terms, modifying only the provisional pricing as reflected in the
final contract. The Court emphasized that an arbitration agreement need not be
formally signed if the parties’ conduct, correspondence, and performance
clearly manifest consent, citing precedents including Govind Rubber Ltd. v.
Louis Dreyfus Commodities Asia Pvt. Ltd. and Caravel Shipping Services v.
Premier Sea Foods. The Court also clarified that the referral Court under
Section 45 need only be satisfied prima facie of the existence of an arbitration
agreement, leaving full adjudication to the arbitral tribunal. Consequently,
the arbitration clause in Contract No. 061-16-12115-S was found valid and
binding, and the appellant was entitled to invoke it for resolution of
disputes.
ANALYSIS:
The present case underscores the principle
that the validity of a contract and its arbitration clause cannot be negated
solely on the ground of an unsigned agreement when the parties’ conduct clearly
indicates acceptance and performance. Despite respondent No.1 not signing
Contract No. 061-16-12115-S, its actions, including accepting 2,000 metric tons
of zinc, raising invoices referencing the contract, and facilitating Standby
Letters of Credit, demonstrated unequivocal assent to the terms. The email
exchanges between the parties further reinforced that they were ad idem
regarding the contract’s essential terms, with only minor modifications
incorporated. This shows that in commercial transactions, consent and intent
may be inferred from conduct, correspondence, and performance, rather than
formal signatures alone, aligning with the modern approach to e-commerce and
telecommunication-based agreements.
Moreover, the case highlights the
importance of enforcing arbitration agreements under Section 45 of the
Arbitration and Conciliation Act, 1996, where the court’s role is limited to a
prima facie assessment of the existence of such an agreement. The Supreme Court
emphasized that disputes regarding validity or performance of the contract are
to be fully adjudicated by the arbitral tribunal, not the referral Court. By
restoring the appellant’s application for arbitration, the Court reinforced
that commercial parties cannot evade arbitration by merely withholding a
signature when their conduct otherwise indicates agreement. The judgment thus
strengthens the principle of honouring contractual commitments and promotes the
efficient resolution of disputes through arbitration, preventing parties from
using formalities as a pretext to avoid their obligations.