• Home
  • About
  • Expertise
  • Insight  
  • Blog
  • Career
  • Contact
  • Judgements

    DATE: 17/05/2025

    COURT: High Court of Bombay

    BENCH: Justice Somasekhar Sundaresan

    FACTS:

    Hindustan Petroleum Corporation Ltd. (HPCL), the Petitioner, invited bids for the construction of twelve “mounded bullets”, specialized storage units for liquified petroleum gas, at its refinery located in Mahul, Mumbai. The contract was awarded to G.R. Engineering Private Limited (GRE), the Respondent. Under the terms of the contract, the mounded bullets were required to be constructed using reinforced cement concrete (RCC) of M30 grade, ensuring a specific standard of structural integrity. The Project was originally scheduled to be completed by December 5, 2007; however, actual completion occurred only on February 2, 2010. Following completion, disputes arose between the parties regarding the deductions made by HPCL from GRE’s invoices. HPCL had levied liquidated damages citing delay in project completion and also withheld payments under various heads including alleged deficiencies in Civil Works, under-insurance, Customs Duty variation, Service Tax, and other related claims.

    These deductions by HPCL prompted GRE to initiate arbitration proceedings. The Arbitral Tribunal, after evaluating the contractual terms and evidence presented by both parties, rendered an award on May 2, 2018, largely in favour of GRE. The Tribunal found that the withholdings made by HPCL, including Rs. 1,99,07,227 for Civil Works, Rs. 25,64,026 for under-insurance, Rs. 86,38,491.50 for Customs Duty variation, Rs. 3,08,85,583 for Service Tax, Rs. 5,00,000 for normalising ‘Dished Ends’, and Rs. 5,83,67,973 towards liquidated damages were unjustified. The Tribunal directed HPCL to release these amounts to GRE and also awarded interest at the rate of 7% per annum from the date of the claim filing (September 6, 2012) until the date of actual payment. HPCL, dissatisfied with the findings and alleging perversity in the arbitral decision, challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, leading to the present proceedings.

     

    ISSUES:

    The primary issues presented before the Court in this Section 34 petition were whether the arbitral award suffered from perversity or patent illegality in relation to various heads under which HPCL withheld payments from GRE. Specifically, the challenge focused on (i) the arbitrability of disputes concerning Civil Works, (ii) the Tribunal's reliance on expert evidence not introduced by HPCL, (iii) the Tribunal's rejection of HPCL’s claim for liquidated damages despite a contractual provision allowing them, and (iv) whether the Tribunal erred in directing the computation of Customs Duty based on exchange rates in the bills of entry rather than the base date.

    JUDGEMENT WITH REASONING:

    The Bombay High Court upheld the arbitral award in all respects except for the element concerning liquidated damages. It quashed the Tribunal’s findings on liquidated damages for being devoid of reasons and remitted this specific issue for re-arbitration. All other findings, including those on Civil Works, under-insurance, Service Tax, and Customs Duty, were affirmed. The Court directed that any amounts deposited in Court be released to GRE after deducting liquidated damages and disposed of the petition without imposing costs.

    The Court found no perversity or illegality in the Arbitral Tribunal's conclusions regarding the withheld amounts under Civil Works, under-insurance, Service Tax, and Customs Duty. It held that HPCL's own vigilance department could not be equated with a "government agency" under Clause 8.b of the General Conditions of Contract, and therefore, the dispute was arbitrable. The Court also rejected HPCL’s objection to the reliance on the Jangid Report, observing that since arbitration is not bound by strict rules of evidence, the Tribunal was within its rights to consider the report, especially when it was based on a study commissioned by HPCL itself. The Jangid Report and Sinha Report were consistent in concluding that the Civil Works met the required M30 concrete standard, and the Tribunal's reliance on these findings was considered reasonable and within its jurisdiction. Similarly, the Tribunal’s interpretation that Customs Duty must be computed using exchange rates on the bills of entry was found to be intelligible and not vague, as alleged by HPCL.

    However, the Court took exception to the Tribunal’s treatment of the claim concerning liquidated damages. It held that the Tribunal failed to analyse key aspects such as causation of delay, whether it was difficult or impossible to prove actual loss, and whether the contractual stipulation of 0.5% per week (capped at 5%) was reasonable. The Tribunal had merely acknowledged that some loss would naturally occur due to delay but provided no examination of whether HPCL had substantiated the loss or whether GRE was actually responsible for the delay. The Court referenced Kailash Nath v. DDA to underscore that forfeiture of amounts without evidence of loss or an enquiry into causation may not be sustained in law. It noted that the Tribunal had failed to engage with the relevant case law or undertake the necessary legal analysis. As a result, it quashed the Tribunal’s findings on liquidated damages and allowed this issue to be resolved afresh through arbitration.

    ANALYSIS:

    This case presents a significant reaffirmation of the limited scope of judicial intervention under Section 34 of the Arbitration and Conciliation Act, 1996. The Bombay High Court meticulously reviewed the arbitral award and upheld the principle that courts should not reappreciate evidence or substitute the arbitrator’s plausible view with their own, unless findings are perverse or contrary to the fundamental policy of Indian law. The Court accepted the Arbitral Tribunal’s reasoning on major financial disputes, including Civil Works, Customs Duty, and Service Tax, affirming that GRE had met the required M30 RCC standard. The Court particularly emphasised that HPCL’s internal vigilance department could not be equated to an external “government agency,” thereby maintaining the arbitrability of the dispute. Additionally, the reliance on expert reports, despite procedural objections—was deemed justified, since the Tribunal considered material findings from both the Jangid and Sinha Reports without procedural impropriety.

    However, the judgment also underscores the necessity for reasoned decision-making in arbitral awards, particularly when dealing with liquidated damages. The High Court found the Tribunal’s analysis inadequate for failing to address critical elements such as the attribution of delay, difficulty of proving actual loss, and the reasonableness of the stipulated damages. The omission to analyse the causation of delay or engage with binding precedents such as Kailash Nath v. DDA amounted to a serious lapse, justifying partial interference. In doing so, the Court struck a careful balance between judicial restraint and the need for sound arbitral reasoning. This nuanced approach reinforces the autonomy of arbitral tribunals while making it clear that bare contractual enforcement without legal analysis cannot withstand scrutiny under Section 34.

    Our Services

    If You Need Any Help
    Contact With Us

    info@adhwaitha.com

    View Our More Judgmental