• Home
  • About
  • Expertise
  • Insight  
  • Blog
  • Career
  • Contact
  • Judgements

    DATE: 24/09/2025

    COURT: Supreme Court of India

    BENCH: Justice Manoj Misra and Justice Ujjal Bhuyan

    FACTS:

    The dispute arose out of a Memorandum of Understanding (MoU) executed on April 9, 2014, between PBSAMP Projects Pvt. Ltd. (appellant) and HLV Ltd. (respondent) concerning the sale of land in Banjara Hills, Hyderabad. Under the MoU, the respondent paid an advance of Rs.15.5 crores to the appellant. As disputes surfaced, the MoU was terminated, and the matter was referred to arbitration. A three-member arbitral tribunal, presided over by Justice Arijit Pasayat, passed an award on September 8, 2019. The tribunal directed the appellant to refund Rs.15.5 crores with interest at 21% per annum from the dates of payment until repayment. The tribunal expressly noted that this rate and duration were in accordance with the terms of the MoU and rejected the appellant’s counterclaim.

    The appellant’s challenge to the award under Section 34 of the Arbitration and Conciliation Act, 1996, was dismissed in March 2021, and the award attained finality. During execution, the appellant paid Rs.44.42 crores, claiming it was full satisfaction of the award. The respondent, however, claimed entitlement to compound interest over and above the awarded 21% simple interest. The executing court rejected this plea, holding that the award had not granted compound interest and that the paid amount satisfied the decree. On revision, the Telangana High Court set aside the executing court’s order and remanded the matter for reconsideration. Aggrieved, the appellant approached the Supreme Court.

    ISSUES:

    The central issue before the Supreme Court was whether the respondent, as decree holder, was entitled to interest upon interest (compound or post-award interest) under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996, despite the arbitral tribunal having already awarded simple interest at 21% per annum until repayment in accordance with the MoU.

     

    JUDGEMENT WITH REASONING:

    The Supreme Court set aside the Telangana High Court’s order dated April 22, 2024, and restored the executing court’s order dated November 2, 2023. It held that the respondent was not entitled to compound interest or post-award interest, as the arbitral tribunal had already determined the applicable rate and duration of interest under the terms of the MoU.

    The Court reasoned that Section 31(7)(a) of the Arbitration Act explicitly gives primacy to party autonomy, allowing parties to decide the interest regime in their agreement. In this case, Clause 6(b) of the MoU expressly provided for repayment of advances with simple interest at 21% per annum until repayment in the event of termination. The arbitral tribunal faithfully applied this contractual provision, awarding interest until repayment, thereby exhausting its discretion under Section 31(7)(a). Once the tribunal specified both the rate and the duration, there was no scope for invoking Section 31(7)(b) to grant any additional or compound interest. The Court clarified that the principle in Hyder Consulting (UK) Ltd. v. State of Orissa, where post-award interest was permitted, would apply only where the tribunal had left the matter open or remained silent on interest. Here, the tribunal was neither silent nor ambiguous.

    The Court further emphasized that the MoU did not contemplate compounding of interest, nor did the arbitral tribunal grant such relief. To permit the respondent to claim compound interest at the execution stage would effectively rewrite the award, which is impermissible. The Court noted that arbitration is rooted in party autonomy and the finality of awards, and courts cannot expand or alter the scope of an arbitral award during enforcement. Reliance on S.A. Builders Ltd. and other precedents was held to be misplaced, as those cases dealt with scenarios where the contractual or arbitral silence necessitated statutory application of Section 31(7)(b). In the present case, both the contract and the award explicitly settled the matter of interest, leaving no room for judicial modification. Hence, the executing court was correct in holding that the appellant’s payments discharged the award in full.

    ANALYSIS:

    This case highlights the Supreme Court’s strict adherence to the principle of party autonomy in arbitration and the finality of arbitral awards. By holding that the respondent could not claim compound or post-award interest, the Court reaffirmed that where the parties have expressly agreed upon the interest regime, and the arbitral tribunal has given effect to it, neither Section 31(7)(b) of the Arbitration and Conciliation Act nor judicial interpretation can override those terms. The decision draws a clear line between cases where an arbitral tribunal is silent on interest, allowing statutory provisions to apply and cases where the contract and award comprehensively address the rate and duration of interest. This distinction is vital to maintaining the sanctity of contractual bargains and the limited supervisory role of courts in arbitral enforcement.

    The ruling also underscores the Court’s commitment to preventing post-award litigation strategies that attempt to expand the scope of arbitral awards during execution. By rejecting the respondent’s plea for compound interest, the Court protected the efficiency and certainty of arbitration, cautioning against reopening settled issues under the guise of enforcement. The reliance on precedents such as Hyder Consulting and S.A. Builders was carefully distinguished, emphasizing that judicial expansion of interest provisions would not be permissible where the tribunal had already acted within its mandate. In essence, the judgment strengthens predictability in commercial arbitration, ensuring that enforcement proceedings remain confined to the terms of the award rather than becoming a forum for renegotiation.

    Our Services

    If You Need Any Help
    Contact With Us

    info@adhwaitha.com

    View Our More Judgmental