The Supreme Court on Friday, January 30,
held that the scale of a company’s operations including its turnover,
production volume, or revenue generation can be a relevant and decisive factor
in assessing environmental damage compensation. The ruling was delivered by a
bench comprising Justice Dipankar Datta and Justice Vijay Bishnoi while
upholding orders of the National Green Tribunal (NGT) imposing substantial
penalties on real estate developers for environmental violations arising from
illegal and unauthorised construction activities.
The appeals before the Court arose from
separate NGT orders directing Rhythm County to pay ₹5 crore and Key Stone
Properties to pay approximately ₹4.47 crore as environmental compensation for
breaches of environmental laws during the execution of large residential
projects in Pune. In determining the quantum of compensation, the NGT had taken
into account the developers’ scale of operations and project costs.
Before the Supreme Court, the developers
challenged the NGT’s approach, arguing that there was no statutory formula
empowering the tribunal to quantify environmental compensation based on
turnover or project cost. They contended that reliance on such factors was
arbitrary and that the compensation framework evolved by the Central Pollution
Control Board (CPCB), which is primarily tailored for industrial polluters,
could not be extended to residential real estate projects. It was further
alleged that the NGT had merely adopted Joint Committee reports without
independent application of mind, thereby abdicating its judicial
responsibility.
Rejecting these submissions, the Supreme
Court affirmed that in environmental protection cases, linking the scale of a
company’s operations to the extent of environmental harm is both logical and
necessary. The Court reasoned that larger operations typically entail greater
resource consumption, higher emissions, and increased waste generation, which
collectively place greater stress on the environment. Where a company derives
greater profit from its scale, it must correspondingly shoulder a higher responsibility
for the environmental costs it imposes. Such an approach also serves as a
deterrent by signalling that larger entities are expected to adhere to stricter
environmental standards.
The judgment, authored by Justice Datta,
noted that the NGT had consciously adopted project cost as a relevant benchmark
for quantifying compensation and that this approach was consistent with
established legal principles. The Court clarified that the CPCB framework does
not exclude consideration of project cost or turnover, and its adoption does
not become invalid merely because alternative metrics could also have been
employed.
The Supreme Court placed reliance on its
earlier decision in Goel Ganga Developers India Pvt. Ltd. v. Union of India
(2018), where environmental compensation in the range of 5 to 10 percent of the
project cost was approved for serious violations. Applying this precedent, the
Court found that the penalties imposed on both Rhythm County and Key Stone
Properties were well within the accepted benchmark and could not be
characterised as excessive or disproportionate.
In the case of Rhythm County, the NGT had
recorded clear findings of construction without mandatory statutory
permissions, continuation of work despite stop-work orders, and deviations from
sanctioned plans. Considering these factors, the tribunal enhanced the
compensation by using project cost as the relevant yardstick to ensure a
rational connection between the scale of the project and the objectives of
environmental restitution and deterrence. The Supreme Court held that the NGT
had acted well within its statutory authority.
With respect to Key Stone Properties, the
Court noted that the NGT had distinguished between violations already covered
under a one-time violation window and separate infractions involving prolonged
construction without consent to establish, continuation despite closure
directions, and occupation without consent to operate. Based on the nature,
duration, and gravity of these violations, the NGT’s reliance on the CPCB
methodology was found to be appropriate.
The Court reiterated that environmental
compensation must be grounded in rationality, proportionality, and a reasoned
assessment. While turnover or project cost cannot be applied mechanically, they
remain permissible and relevant factors depending on the factual context.
Finding no infirmity in the NGT’s approach and affirming adherence to the
polluter pays principle, the Supreme Court dismissed the appeals and upheld the
penalties imposed.