The Delhi High Court has expressed deep regret over the
prolonged litigation faced by low-paid Group-D employees working as
commission-based bearers and vendors in the Railways, while dismissing two writ
petitions filed by the Ministry of Railways challenging their regularisation. A
Division Bench comprising Justice C. Hari Shankar and Justice Om Prakash Shukla
upheld the November 7, 2016 order of the Central Administrative Tribunal (CAT),
which had directed the Railways to regularise the employees, pay them arrears
of minimum pay scales along with applicable allowances from November 14, 2000,
and bear costs of ₹1 lakh.
The Court observed that it was a matter of serious concern
that employees receiving low wages had been compelled to litigate for decades
to secure their legitimate entitlements, despite repeated directions issued by
the Supreme Court. The Bench noted that the employees had continued to perform
their duties for several years and that their claims to regularisation were
supported by a Railway Board Circular dated December 13, 1976, which
contemplated the progressive absorption of commission-based vendors against
regular vacancies.
The respondents had been working as commission-based bearers
and vendors under the North Eastern Railway. Their claim for regularisation had
also been considered in the light of several decisions of the Supreme Court,
including Mahesh v. Union of India (1987) and South Eastern Railway Congress v.
Chairman, Railway Board (1997). Subsequently, the Railway Board issued a
circular in 2005 relaxing the educational qualification requirements applicable
to such workers. Despite these developments and the directions issued by the
Supreme Court, the employees remained without permanent status for several
years.
The workers approached the CAT in 2013 and 2014 seeking
appropriate relief. By its order dated November 7, 2016, the Tribunal directed
their regularisation, payment of the minimum pay scale with allowances from
November 14, 2000, and payment of ₹1 lakh towards costs. The Union of India
subsequently challenged the Tribunal's decision before the Delhi High Court.
While examining the matter, the High Court took note of the
Railways' claim that several of the employees had already been absorbed as
Group-D workers. However, the Court found that the Railways had failed to
substantiate this assertion. It further noted that contradictory statements had
been placed before both the Tribunal and the High Court. The Bench described
the lack of candour in the Railways' submissions as disturbing and accepted the
respondents' contention that none of them had actually been regularised despite
the repeated judicial directions.
The Court further relied on recent Supreme Court decisions
concerning long-term temporary employment and observed that workers
continuously performing essential and perennial duties cannot be kept
indefinitely in an ad hoc or temporary arrangement. It held that such prolonged
continuation in temporary employment could amount to an unfair labour practice
and implicate the protection guaranteed under Article 21 of the Constitution.
Since it was undisputed that the respondents fell within the relevant category,
the Court found no justification for subjecting them to a further screening
process for regularisation.
The Bench also upheld the ₹1 lakh costs imposed by the
Tribunal. It observed that, if there had been any error in the quantum of
costs, the Tribunal had erred on the side of leniency. The Court emphasised the
responsibility of courts to protect the interests of economically weaker
sections and persons receiving very low wages, noting that such protection was
consistent with the socialist character of Indian democracy contemplated by the
Preamble.
Accordingly, the High Court dismissed the Railways' writ
petitions and directed the Union of India to implement the Tribunal's order by
regularising the concerned employees, paying the arrears of minimum pay scales
and allowances from November 14, 2000, and disbursing the awarded costs within
four weeks. The Court further directed that, in the event of non-compliance
within the stipulated period, the Tribunal would immediately revive the pending
contempt proceedings.