The Supreme Court has recently introduced a
significant and controversial shift in its interpretation of Section 29A(5) of
the Arbitration and Conciliation Act, 1996, by permitting post-award extensions
of an arbitral tribunal’s mandate, thereby rendering awards enforceable even
when they were delivered beyond the statutory time limit. In C. Velusamy v. K.
Indhera (2026 LiveLaw (SC) 105), a two-judge Bench held that an application
seeking extension of an arbitrator’s mandate under Section 29A(5) remains maintainable
even after an arbitral award has been passed beyond the prescribed period, and
that such an extension may operate retrospectively to validate the award.
This ruling marks a paradigm shift in
India’s arbitration framework. While it reflects the Court’s intention to
prevent technical lapses from overriding substantive justice, it simultaneously
raises concerns about the erosion of procedural discipline and certainty that
Section 29A was introduced to ensure. The provision, inserted through the 2015
Amendment, was designed to curb delays in arbitral proceedings by imposing a
strict timeline. It mandates that an arbitral award be made within twelve
months from the date the tribunal enters upon reference, extendable by a
further six months with the consent of the parties. Upon failure to render an
award within this maximum period of eighteen months, the tribunal’s mandate
automatically terminates under Section 29A(4), unless extended by a competent
court under Section 29A(5).
The controversy surrounding Velusamy stems
from the Court’s reliance on its earlier decision in Rohan Builders (India)
Pvt. Ltd. v. Berger Paints India Ltd. (2024 LiveLaw (SC) 693). In Rohan
Builders, the Court dealt with a pre-award situation where the tribunal’s
mandate had technically expired, but no award had yet been passed. The Court
interpreted the term “termination” in Section 29A(4) to mean that the mandate
could still be revived by a court, allowing the tribunal to proceed and deliver
an award even after the statutory timeline had lapsed.
In contrast, Velusamy involved a
post-award scenario, where the tribunal had already delivered its award after
its mandate had ceased. The core issue was whether an arbitral tribunal lacking
a valid mandate could lawfully pass an award. The Court answered this in the
affirmative, holding that the absence of an express prohibition in Section 29A
against post-award extensions allowed courts to retrospectively validate such
awards. However, Section 29A appears to contemplate extensions only in cases
where an award has not yet been made and time is sought to enable the tribunal
to render one. It does not expressly address situations where an award already
exists but was rendered without authority.
Notably, unlike the Arbitration Act, 1940,
which explicitly empowered courts to extend time even after an award was made,
the 1996 Act contains no such curative provision. This legislative omission
suggests a conscious departure from the earlier regime. By permitting
post-award extensions without explicit statutory backing, the judgment
introduces uncertainty into the post-award landscape.
The Court characterized awards passed after
expiry of the tribunal’s mandate as not void but unenforceable until validated
by a judicial extension. It further indicated that such awards need not
necessarily be challenged under Section 34. This reasoning has generated
procedural ambiguity, particularly regarding the timing and availability of
remedies. Section 34 provides the sole statutory mechanism to challenge an
arbitral award and is governed by strict limitation periods. If an award is
unenforceable and legally uncertain until the tribunal’s mandate is extended,
parties are left unclear whether they should challenge it immediately or await
judicial validation.
By leaving these questions unanswered, the
judgment risks complicating post-award remedies and undermining the certainty
that arbitration seeks to provide. Greater clarity on the interplay between
Sections 29A, 34, and 36 would have strengthened the ruling and reduced future
litigation. The views expressed are personal.